Permits & Agreements

A Work Permit must be obtained prior to entering onto railroad property owned or operated by Chesapeake and Delaware, LLC (C&D).

In most situations, an existing Right of Way Agreement is required as a precedent to obtaining a Work Permit. The process for obtaining a Right of Way Agreement varies for each of our railroads, depending on the owner of the right of way.

Please scroll down for links to our application forms and additional information.

Application Forms

Work Permits

To ensure on-track safety, a Work Permit will be required for any entity wishing to access railroad property.

In order to begin the Work Permit process, please submit a Work Permit Application by clicking on the link below.

A non-refundable document preparation and processing fee of $1,500.00 must be paid prior to receiving a Work Permit. You will be invoiced upon submitting a completed application form.

Right of Way Agreements

In most cases, an existing Right of Way Agreement will be required as a precedent to receiving a Work Permit.

Situations that require a Right of Way Agreement include, but are not limited to, utility crossings, private grade crossings, right of entry requests, leases, and other permanent encroachments on the railroad right of way.

The process for obtaining a Right of Way Agreement will vary for each of our railroads, based on the owner of the right of way.

Please submit a Right of Way Agreement Application by clicking on the link below, and one of our team members will be in touch with information on the next steps for your request.

Additional Information

  • For Work Permits, a non-refundable document preparation and processing fee of $1,500.00 applies.

    You will be invoiced upon submitting a completed application form.

    Fees for Right of Way Agreements will vary based on the nature of the access request.

  • In most situations, applicants will be require to provide proof of the following types of insurance:

    • Commercial General Liability Insurance with limits of no less than $2 million per occurrence / $6 million aggregate.

    • Railroad Protective Liability Insurance with limits of no less than $2 million per occurrence / $6 million aggregate.

    • Worker’s Compensation Insurance with limits of no less than $1 million.

    • Automobile Liability Insurance with limits of no less than $1 million.

    Coverage requirements may vary depending on the nature of the project, and will be confirmed upon receipt of your Application.

  • Please refer to our C&D System Wire, Conduit and Cable Standards and our C&D System Pipeline Standards as needed to answer questions regarding permitted engineering and design standards.

  • For Right of Way Agreements, applicants will be asked to provide drawings, plans and/or maps of any planned improvements.

  • If workers will be within 10 feet of the right of way working during the hours of regular scheduled train movements, railroad worker protection is required at $500 per day.

    Railroad worker protection needs must be communicated as soon as possible for adequate protection and staffing.

    If required by Federal law, based on the scope of the work being performed on railroad property, we will assign an inspector and/or roadway worker in charge to observe work and/or provide the required protections for workers against rail movements.

    The cost of inspectors and/or roadway workers in charge will be billed to the Work Permit applicant. Such costs will be advised in advance of the Work Permit being issued.